Rucker Renewal Project Updates

Posted on: September 6, 2019

Rucker Renewal project update 9-6-19

Rucker project logo

THIS WEEK


Hoyt

The contractor began constructing sidewalks, continued pouring curbs and installed traffic detecting loops. 

Rucker construction 9-6-19

Rucker

The contractor installed storm drain on Hewitt and demolished and graded the roadway from California to Hewitt. Phase 2 waterline work included laying pipe from Hewitt to Pacific.

Wall 

Wall Street was closed during waterline installation across Wall. This work was anticipated to take 2 to 3 days, but conditions under the pavement required additional work to install the waterline. Once across, Wall will be reopened.

UPCOMING

Hoyt

The contractor will complete the east sidewalk with the paving over of the Frontier vault lid. On the west side, the contractor will demolish existing sidewalks, auger signal and light pole bases,  put in conduit and junction boxes and install irrigation.

Rucker

The contractor will continue to lay storm drain pipe on Hewitt, demolish and grade from California to Hewitt and install electrical and irrigation crossings. Concrete roadway paving will begin.

Wall 

Wall Street will be closed while the waterline is being installed across Wall. This is anticipated to until September 11. Once across, Wall will be reopened.

REMINDERS

The Phase 2 waterline work continues and will be ongoing. Rucker will remain in an open-to-local-access only but closed to through traffic for the foreseeable future.

The Hewitt/Rucker intersection will remain closed until the completion of Phase 1 work, sometime this fall. A pedestrian detour route will be available through the area. Vehicular access on Rucker Avenue between Hewitt and Wall will also remain open, including turnaround space at the top (north end) of the roadway. A flagger will be present at the Hewitt/Rucker intersection at all times. Traffic will be restricted to one lane in each direction from Pacific to Wall; restricted to local business/residential access only from Wall to Hewitt. No through traffic will be allowed. The signed detour that has been in place will remain.

During the waterline work, there will be intermittent loss of water service for several hours at a time. The contractor will notify customers prior to service interruptions.

Future closures of the Rucker and Everett Avenue intersection will occur later in the project in support of the waterline work.

Business support

The City’s tourism channels (VisitEverett.com, facebook.com/visiteverett, instagram.com/visiteverett) have begun highlighting stakeholders impacted by the Rucker Renewal project, and yours could be next. If you're interested in your business being featured, please contact Julio Cortes at 425-257-7110.

Construction liaison info

Pedestrian access

The contract provides for an ADA compliant 6-foot protected and lighted pedestrian path, and any pedestrian detours will be signed. Pedestrians are discouraged from traveling in the work zone, but when necessary, the contractor is required to provide escorts during work hours.

Business entrances 

Business entrances will always be accessible either via an existing sidewalk or a temporary asphalt sidewalk.

Work hours

Project work hours are 7 a.m. to 5 p.m., with possible evening work. Everett’s noise ordinance prohibits work between 10 p.m. and 7 a.m. during the week and between 6 p.m. and 8 a.m. on weekends unless a variance has been issued.

Historical findings

See images of historical finds from the Rucker Renewal project in the photo gallery.

Facebook Twitter Email

Other News in Rucker Renewal Project Updates

Rucker project logo

Rucker Renewal project update 11-18-19

Posted on: November 15, 2019
Rucker project logo

Rucker Renewal project update 11-8-19

Posted on: November 1, 2019
Rucker project logo

Rucker Renewal project update 11-1-19

Posted on: November 1, 2019
Rucker project logo

Rucker Renewal project update 10-25-19

Posted on: October 25, 2019
Rucker project logo

Rucker Renewal project update 10-18-19

Posted on: October 18, 2019
Rucker project logo

Rucker Renewal project update 10-11-19

Posted on: October 11, 2019
Rucker project logo

Rucker Renewal project update 10-4-19

Posted on: October 4, 2019
Rucker project logo

Rucker Renewal project update 9-27-19

Posted on: September 27, 2019
Rucker project logo

Rucker Renewal project update 9-20-19

Posted on: September 20, 2019
Rucker project logo

Rucker Renewal project update 9-13-19

Posted on: September 13, 2019
Rucker project logo

Rucker Renewal project update 8-30-19

Posted on: August 30, 2019
Rucker project logo

Rucker Renewal project update 8-23-19

Posted on: August 23, 2019
Rucker project logo

Rucker Renewal project update 8-16-19

Posted on: August 16, 2019
Rucker project logo

Rucker Renewal project update 8-9-19

Posted on: July 22, 2019
Rucker project logo

Rucker Renewal project update 8-2-19

Posted on: July 22, 2019
Rucker project logo

Rucker Renewal project update

Posted on: July 12, 2019
1914 Sanborn historic map

Rucker Renewal project update

Posted on: July 1, 2019