Grand Avenue Park Bridge Project Updates

Posted on: July 19, 2018

[ARCHIVED] Grand Avenue Park Bridge June/July 2018 Construction Update

East abutment concrete pour

June/July 2018

Grand Avenue Park Bridge project update

Complete

  • Rebar preparation, forms, and concrete pours for the uppermost portion of the tower.
  • Rebar preparation, forms, and concrete pours for the east abutment of the bridge at Grand Avenue Park.
  • Removal of sheet piles.

In Process

  • Rebar preparation, forms, and concrete pours for the uppermost portion of the tower.
  • Reviews and approvals of bridge steel shop drawings, bridge lighting, and mock-up of the guard rail.
  • Steel bridge pieces are being manufactured and then assembled in a large bay at the mill in Vancouver, Washington. The Washington State Department of Transportation is inspecting this process.
  • Contractor is awaiting approval of the Bridge Erection Plan from BNSF Railway. Application was also made for widening the private railroad crossing for the bridge erection.
  • Installation of large diameter pipelines in West Marine View Drive. This work has a reduction to one lane of traffic at times due to the depth and extent of excavation. Estimated completion by the 4th of July, with paving anticipated on July 2nd (weather dependent).

Upcoming

  • Frontier will be installing a crossing for elevator communication. This work will involve lane closures on West Marine View Drive. This work will not begin until after the current traffic control for one-lane flagging is no longer needed.
  • The elevator is in the process of being manufactured and scheduled for delivery approximately September 1st.