- Home
- Your City
- Departments
- Public Works
- Construction Projects
- Sewer O Utility Project
Sewer O Utility Project
This project, located in the Port Gardner neighborhood, will replace 100 plus-year-old sewer pipes and increase capacity. Additional improvements include replacing cast iron water mains and street illumination wiring systems.
Map this project on the interactive project overview story map.
Sewer “O” Utility Upgrades project will replace and upsize existing sewers to address pipe condition and capacity issues. Existing drainage structures in the right of way will be replaced and reconnected to the new main.
Aging cast iron water mains installed in 1958 are prone to breaks and will be replaced on Colby Ave between 37th and 40th. Street illumination wiring and telemetry conduit will be replaced. Restoration will include trench patch, half width street pavement overlay of the east side of Colby Avenue, ADA curb ramp upgrades at intersections and replacement of sidewalk both sides of the street. Alleys will be repaved full width after trenches are backfilled.
See Sewer O planning map for location of improvements.
The work will occur in three locations:
- Area 1 - Colby Avenue from 37th to 40th Streets
- Area 2 - Lombard / Oakes alleyway 32nd to 33rd Streets
- Area 3 - Oakes / Rockefeller alleyway 32nd to 34th Streets
Work in area 1 involves upgrades to existing sanitary sewer and side sewers to residences and businesses, storm sewer, watermain and water services, street lighting and ADA curb ramps. Work in areas 2 and 3 involves replacement of existing sewer mains and side sewers, installation of storm drainage and repaving of alleyways.
Alley from 35th-36th between Lombard and Broadway: Completed.
Phase 1 Design Phase Complete: April 2020
Phase 1 Construction Start: August 2020
Phase 1 Construction Completion: April 2021
The Contractor will begin working in areas 1 and 2 simultaneously. Once work in area 2 is complete, work will proceed to area 3. Work in areas 2 and 3 is anticipated to be complete by end of October.
Work in area 1 will continue through the end of 2020. Restoration of street resurfacing will occur in early spring of 2021, to allow for better weather to complete final project restoration. Little or no activity will occur during the winter months where.
Phase 2: Currently in the preliminary design phase. A separate webpage will be created for Phase 2 at a later date.
Community Project Liaison
Joshua Gaethle
Interwest Construction
Email
Project supervisor
Lance Husby
Everett Public Works
Phone: 425-257-8862
Email
Project Manager
Amie Roshak, P.E.
City of Everett, Public Works
Phone: 425-257-7249
Email
Construction Manager
Tom Fuchs
City of Everett, Public Works
Phone: 425-257-8931
Email
-
Amie Roshak
Project ManagerPhone: 425-257-7249
-
Tom Fuchs
Construction ManagerPhone: 425-257-8931